Projects / Civil

Pump Station 4 Force Main River Crossing

The existing sewer force main under the Wishkah River failed, and the City of Aberdeen needed it back before sewage reached the river. Cannon installed a new 12 inch HDPE SDR 11 force main 600 feet under the river by horizontal directional drilling, so the riverbed was never opened and surface impact stayed minimal. Cannon ran wireless steering to hold line through brackish water interference, coordinated the work with the City, WSDOT and the general contractor, and finished ahead of schedule.

Services Employed:

  • 600 feet of 12 inch HDPE SDR 11 force main installed under the Wishkah River by horizontal directional drilling
  • Riverbed kept closed and surface disturbance held to a minimum on a high profile emergency
  • Wireless steering run to hold line through brackish water interference
  • Planned and executed inside an emergency timeline to prevent environmental and service disruption
  • Daily coordination with the City of Aberdeen, WSDOT and the general contractor
  • Habitat protected through construction and the crossing left with minimal disturbance
  • Sewer system integrity restored and reliable service returned to the community
  • Finished ahead of schedule