Projects / Directional Drilling
Charter Spectrum WR14 Rock Drilling
Charter Communications brought Cannon in for the hardest part of the WR14 build: horizontal directional drilling through solid rock along a winding road with restricted setup areas. Cannon drove 20 bores totaling 5,362 feet, pulled in 2 inch HDPE for the communication lines, held 300 feet a day in rock ground conditions, and closed the entire scope in 18 working days in the spring of 2024.
Services Employed:
- 20 bores totaling 5,362 feet driven through solid rock in 18 working days
- Averaged 300 feet per day in rock ground conditions
- 2 inch HDPE communication conduit installed
- Ditches plated with 4 by 8 steel plates to build drill setups on a winding road with restricted access
- Bores shortened to hold line through tight radius conditions
- Drill and all support equipment supplied, including mini excavator, single reel carrier and water source
- All bore mud vacuumed, hauled and disposed of
- Bore profile delivered at completion
More Directional Drilling work
Related projects
PowerKing County PSERN Power Extension
King County, WA | Power
Power extension for the King County Puget Sound Emergency Radio Network, carrying 15kV primary from the public utility district to a radio antenna site...
View project
Directional DrillingCenturyLink El Dorado County Fiber Route
El Dorado County, CA | Directional Drilling
Cannon directional drilled and placed 20,000 feet of underground fiber optic conduit across El Dorado County to carry CenturyLink's network expansion through the Sierra...
View project
CivilPump Station 4 Force Main River Crossing
Aberdeen, WA | Directional Drilling
The existing sewer force main under the Wishkah River failed, and the City of Aberdeen needed it back before sewage reached the river. Cannon...
View project