King County PSERN Power Extension
Power extension for the King County Puget Sound Emergency Radio Network, carrying 15kV primary from the public utility district to a radio antenna site so the county's emergency communications network had a permanent power feed. Cannon executed 14,000 feet of directional bore to place the primary underground across the route, avoiding surface disturbance and the terrain between the utility and the site. Junction and transformer vaults were set along the bore path, 15kV conductors installed and terminated, and the extended system tested and turned up before the county took the feed into service.
Services Employed:
- 14,000 feet of directional bore for the 15kV primary extension
- 15kV primary system extended from the public utility district to the antenna site
- Junction vaults set along the route
- Transformer vaults set and grounded
- 15kV conductor installed and terminated
- Comprehensive system testing and turn up
- Coordination with the public utility district at the point of service
- Permanent power delivered to the emergency radio network site
More Power work
Related projects
Power
JBLM Grounding and Lightning Protection, 10 Facilities
JBLM, WA
Grounding and lightning protection system upgrade across ten facilities at Joint Base Lewis-McChord, enhancing the safety and compliance of critical military buildings against lightning...
View projectPower
Iron Mountain Quarry Line Extension
Granite Falls, WA
Half mile electrical line extension at an operating rock quarry in Granite Falls, built overhead and underground up a rock face to a new...
View projectPower
JBLM Overhead Neutral Replacement, McChord Field
JBLM, WA
Replacement of primary neutral conductor across the McChord Field distribution system at Joint Base Lewis-McChord, performed for City Light & Power JBLM under its...
View project
Planning something similar?