Projects / Power

Seattle City Light Joint Use Program

  • WhereSeattle and King County, WA
  • Discipline Power

Cannon has held Seattle City Light's joint use work since 2016, a continuing program of make ready and pole replacement across Seattle and King County released monthly against the master service agreement. The program replaces and upgrades primary distribution poles so the system can carry added telecommunication infrastructure, fiber optic cable and 4G, 5G and small cell antennas, and replaces aging or damaged distribution and transmission structures on systems from 26.4kV up to 115kV. The joint use program has covered more than 3,000 poles and 321 antenna sites, alongside a pole replacement program running since 2019 that covers 1,697 poles. Cannon also answers storm and emergency response releases alongside the scheduled work.

Services Employed:

  • Monthly joint use releases carried continuously since 2016
  • Replacement and upgrade of primary distribution poles for added telecom attachments
  • Distribution and transmission pole replacement on 26.4kV through 115kV systems
  • Pole framing, transformer change outs and wiring adjustments per work order
  • Fiber optic cable and 4G, 5G and small cell antenna support
  • Storm and emergency response releases alongside the scheduled program
  • Work orders managed to budget and schedule across Seattle and King County
  • Agreement extended by the utility through FY27, the eleventh consecutive renewal since 2016

More Power work

Related projects

Planning something similar?

Our estimators and project managers can walk you through approach, schedule and scope.