Projects / Outside Plant

Zayo – Fiber Relocate

Removed a fiber optic vault and duct bank and suspended aerially to accommodate a Fish Culvert placement by the Washington State Department of Transportation under I-405. All work required removal of a concrete encasement and conduit encompassing the active fiber without any outages

Services Employed:

  • Removal & Replacement of a 444LA utility vault
  • Relocation of multiple live fiber optic cables
  • Temporary placement of aerial strand and ecology blocks to support the fiber
  • Final split duct placement to the fiber cables and restored affected areas