One of six federal projects Cannon had running at once, the Beale Air Force Base job in Northern California combined outside plant and inside plant on one contract: 35,000 feet of trenching, 55 manholes and handholes, 74,000 feet of Maxcell and 280,000 feet of fiber optic cable, with the inside plant wiring carried into 120 buildings.
Services Employed:
- 35,000 feet of trenching
- 55 manholes and handholes placed
- 74,000 feet of Maxcell placed
- 280,000 feet of fiber optic cable placed
- Inside plant wiring of 120 buildings
More Federal work
Related projects
FederalMcChord Field CITS Telecommunications Infrastructure Upgrade
McChord Field, WA | Telecommunications
Cannon was contracted by General Dynamics to execute a comprehensive upgrade to the telecommunications infrastructure at McChord Field, a mission-critical project covering both outside...
View project- Power
JBLM Grounding and Lightning Protection, 10 Facilities
JBLM, WA | Power
Grounding and lightning protection system upgrade across ten facilities at Joint Base Lewis-McChord, enhancing the safety and compliance of critical military buildings against lightning...
View project - Federal
Building 7 Category 6 Premise Wiring
JBLM, WA | Inside Plant
In the modernization of Building 7 at Joint Base Lewis-McChord, Cannon engineered, provisioned and implemented a Category 6 horizontal cable system to replace the...
View project
Planning something similar?
Our estimators and project managers can walk you through approach, schedule and scope.